UPDATE: Bluffs- Resurfacing Pavement

ADDITIONAL UPDATE (9/10/19)

The last phase of the road sealing project (Red Zone), that was previously scheduled for Tuesday, September 17th, has been moved to this Thursday, September 12th.

Monday 9/9 – Yellow (phase 3) – No Change
Tuesday 9/10 – Blue (phase 4) – No Change
Wednesday 9/11 – Green (phase 1) – New Date
Tuesday 9/17 Thursday 9/12– Red (phase 2) – New Date

The pavement in the Siver Lake Bluffs will be resurfaced September 9 – September 12. All vehicles need to be removed from the color-coded work areas by 7:30 am on the day work is being done for that section. Any vehicles not removed by 7:30 am will be towed at the owner’s expense. This work includes visitor spots, as well. Also, keep in mind any vehicles left in driveways or garages will not be able to leave once the work starts.

The work areas will be closed while the work is being performed during the day. The areas will be opened up by 7 pm that same day.

Street parking restriction will not be enforced during this time to accommodate. Please be courteous (do not block driveways, park on the grass, etc.) and careful if you do choose to park along the street.

We apologize for the inconvenience this may cause, but this is necessary maintenance to protect our streets and avoid more costly repairs later.